GCM-Final | 9/11/2014 | 9/15/2014 | 9/15/2014 | P | PASS |
Dixie Fellows
|
|
|
Calvin ###-####
|
GCM-Final | 9/10/2014 | 9/11/2014 | 9/11/2014 | P | PART |
Dixie Fellows
|
|
|
Kevin ###-####..partial final ok..waiting on grilles and thermostats..will be done by monday
|
GCM-Rough-in | 9/8/2014 | 9/9/2014 | 9/9/2014 | A | FAIL |
Dixie Fellows
|
|
|
Calvin ###-#### ....flex not allowed on fire dampers
|
GCM-Rough-in | 9/5/2014 | 9/8/2014 | 9/8/2014 | A | NR |
Dixie Fellows
|
|
|
Calvin ###-####..fire dampers not ready
|
GCM-Rough-in | 8/19/2014 | 8/20/2014 | 8/20/2014 | A | PASS |
Dixie Fellows
|
|
|
Calvin ###-#### fire wrap on oxygen room inspection request..fire wrap on ducts in osygen room ok
|
GCM-Rough-in | 8/14/2014 | 8/15/2014 | 8/15/2014 | A | PASS |
Dixie Fellows
|
|
|
cover inspection for office and restroom Calvin ###-####..these spaces ok for cover
|
GCM-Rough-in | 8/6/2014 | 8/7/2014 | 8/7/2014 | A | PART |
Dixie Fellows
|
|
|
this is cover inspection lobby North West corner center Jeremy ###-#### ...corridor 4...back part of kitchen..lobby and exhaust fan in elec room ok for cover
|
GCM-Rough-in | 7/21/2014 | 7/21/2014 | 7/21/2014 | P | PASS |
Dixie Fellows
|
|
|
Calvin ###-#### Fire Damper inspection..both fire dampers in drop down ceiling ok..s/f damper in one hr wall ok..ok to insulate rest of ductwork
|
GCM-Rough-in | 7/14/2014 | 7/14/2014 | 7/14/2014 | P | PART |
Dixie Fellows
|
|
|
Calvin ###-#### cover re-inspection for corridors 3, 4...these corridors ok for cover
|
GCM-Rough-in | 7/8/2014 | 7/8/2014 | 7/8/2014 | P | PART |
Dixie Fellows
|
|
|
Calvin ###-#### cover inspection in corridors 3&4....this should have been a conference..met with calvin and troy to discuss damper locations and concerns
|
GCM-Rough-in | 7/7/2014 | 7/8/2014 | 7/8/2014 | A | FAIL |
Dixie Fellows
|
|
|
THIS IS FOR A COURTESY INSPECTION PER DIXIE, Calvin ###-####..need to extend platforms on all attic furnaces to access opening
|
GCB-Courtesy | 7/8/2014 | 7/8/2014 | 7/8/2014 | A | DONE |
Troy James
|
|
|
meet dixie 8:45
|
GCM-Rough In & Pressure Test | 7/3/2014 | 7/3/2014 | 7/3/2014 | P | PASS |
Troy James
|
|
|
Calvin ###-#### Ceiling cover corridor 2, duct sealer corridors 3, 4
|
GCM-Rough-in | 6/25/2014 | 6/25/2014 | 6/25/2014 | P | PASS |
Troy James
|
|
|
Calvin ###-#### ok to cover wing 1, pan wet switch to be installed at final
|
GCM-Rough-in | 6/23/2014 | 6/23/2014 | 6/23/2014 | P | PART |
Dixie Fellows
|
|
|
Calvin ###-#### room fans in corridors 3&4....all rooms in corridors 3 and 4 ok for cover..corridor 2 duct above ceiling all insulated on inside and sealed on outside ok.. all.furnaces above ceilings need secondary drains and elec completed before cover
|
GCM-Rough-in | 6/16/2014 | 6/17/2014 | 6/17/2014 | A | PART |
Dixie Fellows
|
|
|
Calvin ###-#### rough in for room fans..all rooms in corridor #2 to fire wall (door) ok
|
GCM-Rough-in | 5/22/2014 | 5/23/2014 | 5/23/2014 | P | PART |
Dixie Fellows
|
|
|
all rooms in east wing ok for cover..ok to insulate ducts in hallways
|