Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberGCM15-00041
StatusFinaled
Name EvenFlo Heating
Site Address 415 E 42ND ST
Project NameMEC2015-00041
Customer Number 
ePlanReviewNo
Description
Tailwinds Apts.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCM-Final10/30/201510/30/201510/30/2015PPASS
DetailsChad Schwendiman
###-#### - 1st-3rd floors
GCM-Final10/6/201510/6/201510/6/2015PPART
DetailsAlan Hauser
final on 112, 113, and 110
GCM-Final10/5/201510/6/201510/6/2015APART
DetailsChad Schwendiman
Monty ###-#### - 1st-3rd floor apex - temp occupancy okay on center apex from 2hour double doors east including 7 units 1 on the 1st floor and 3ea. on the 2nd and 3rd floors.
GCM-Final9/30/20159/30/20159/30/2015PPART
DetailsBill VanDegrift
18 units east side 3 floors 6 units per floor and the elevator lobby, 9 units will require loclouts on the air handelers.
GCM-Final9/29/20159/29/20159/29/2015PPART
DetailsDixie Fellows
Monty ###-####...ALL DAMPERS ON 1ST--2ND AND 3RD FLOORS OK FOR COVER..THIS IS NOT READY FOR A PARTIAL FINAL
GCM-Final9/28/20159/28/20159/28/2015PPEND
DetailsDixie Fellows
Monty ###-#### - 1st-3rd corridors...unable to meet today..monte wioo reschedule
GCM-Final9/24/20159/25/20159/25/2015PNR
DetailsChad Schwendiman
Monty ###-#### - partial final - 1st - 3rd floors apex
GCM-Pressure Test9/24/20159/25/20159/25/2015APASS
DetailsChad Schwendiman
Monty ###-#### - 2nd & 3rd floor flue - 5lb flue on furnaces okay
GCM-Rough-in8/19/20158/20/20158/20/2015APASS
DetailsDixie Fellows
Monty ###-####...monte needs to add the rooms numbers in the notes
GCM-Rough-in7/30/20157/31/20157/31/2015APART
DetailsDixie Fellows
Monty ###-####..partial 3rd floor apex corridor..from elevator to east corridor ok to cover..all units 2nd and 3rd floor ok for cover..unit on 1st floor 101..ok for cover
GCM-Rough-in7/20/20157/20/20157/20/2015PPART
DetailsDixie Fellows
Monty ###-####..room 101 needs framing at damper....s/f dampers at 2nd and 3rd floor clearances ok (ready to install dampers)...
GCM-Rough-in7/14/20157/14/20157/14/2015PPART
DetailsDixie Fellows
Monte ###-#### - first floor...partial cover for 1st floor apex area...waiting on 2 fire access doors
GCM-Rough-in7/10/20157/13/20157/13/2015PNR
DetailsDixie Fellows
Monty ###-#### - 1st - 3rd floors..monte cancelled
GCM-Rough-in7/6/20157/7/20157/7/2015APASS
DetailsDixie Fellows
Monty ###-#### rough in requested for 2nd and 3rd floors..framing ok at all apex areas
GCM-Rough-in6/24/20156/24/20156/24/2015PFAIL
DetailsDixie Fellows
Monty ###-####..framing not done at dampers
GCM-Rough-in6/22/20156/22/20156/22/2015PPART
DetailsDixie Fellows
Monty ###-####...clearances around s/f dampers on first floor are ok..ready for angles and access doors
GCM-Rough-in6/18/20156/18/20156/18/2015PPART
DetailsDixie Fellows
Monty ###-####
GCM-Rough-in6/15/20156/16/20156/16/2015ACANC
DetailsDixie Fellows
CONFERENCE ONLY: Gary ###-#### - requested inspection with Dixie and Jim Sly, please coordinate...nobody contacted me about this conference
GCM-Rough-in6/16/20156/16/20156/16/2015PFAIL
DetailsDixie Fellows
Per contractor inpsection took place on Monday 6/15/15 but was not called in - inspection scheduled to document inspection from Monday....smoke fire dampers on 1st floor not installed per manuf
GCM-Rough-in6/11/20156/12/20156/12/2015PPEND
DetailsDixie Fellows
Monty ###-####..rescheduled for mon am
GCM-Rough-in5/27/20155/28/20155/28/2015APART
DetailsChad Schwendiman
Monty ###-#### - okay to cover rooms 318 through 323
GCM-Rough-in5/14/20155/14/20155/14/2015PPART
DetailsChad Schwendiman
Monty ###-#### - okay to cover rooms 218-223
GCM-Rough-in5/12/20155/13/20155/13/2015APART
DetailsChad Schwendiman
Monty ###-#### - Contractor has a letter on site from manufacture stating that the dampers can be used if the fire caulking is removed and the damper is returned to it's original state. okay to cover rooms 118-123, and room 222
GCM-Rough-in5/11/20155/11/20155/11/2015PFAIL
DetailsDixie Fellows
Monty ###-####..need a letter from a manufacturer saying it's ok to scrape fire caulking off of fire dampers or of they have to be replaced
GCM-Rough-in4/28/20154/28/20154/30/2015PPEND
DetailsDixie Fellows
DJ ###-#### - east wing..waiting for info from manuf on fire dampers..need framers to install wood at plenums per approved plans
GCM-Rough-in2/25/20152/25/20152/25/2015PPART
DetailsDixie Fellows
BJ ###-#### - CONFERENCE ONLY - No "inpsection type" for conference available..this this was for a conference..met with structural inspectors and architects to discuss fire protection for dryer vents and range exhausts. tankless w/h venting and gas