Final | 3/24/2000 | 3/24/2000 | 3/24/2000 | P | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 03/24/2000 at 07:36:48. Contact: ###-####.
|
Final | 3/16/2000 | 3/16/2000 | 3/16/2000 | P | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 03/16/2000 at 08:10:18. Contact: ###-####. NEED PROT POST..VENT REG TO OUTSIDE
|
Pressure Test | 1/7/2000 | 1/10/2000 | 1/10/2000 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 01/07/2000 at 12:09:38. Contact: ###-####. 2lb. System ok.
|
Rough-in | 1/7/2000 | 1/10/2000 | 1/10/2000 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 01/07/2000 at 12:09:12. Contact: ###-####.
|
Pressure Test | 1/6/2000 | 1/7/2000 | 1/7/2000 | A | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 01/06/2000 at 13:26:41. Contact: ###-####. PT failed.
|
Rough-in | 1/6/2000 | 1/7/2000 | 1/7/2000 | A | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 01/06/2000 at 13:26:04. Contact: ###-####. C/N left.
|
Rough-in | 1/5/2000 | 1/5/2000 | 1/5/2000 | P | FAIL |
Dixie Fellows
|
|
|
Judy ###-####. Correction called Jerry.
|