Final | 11/14/2000 | 11/15/2000 | 11/15/2000 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 11/14/2000 at 17:09:32. Contact: ###-####.
|
Pressure Test | 7/19/2000 | 7/20/2000 | 7/20/2000 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 07/19/2000 at 13:47:15. Contact: ###-####.
|
Pressure Test | 7/17/2000 | 7/17/2000 | 7/17/2000 | P | FAIL |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 07/17/2000 at 11:06:26. Contact: ###-####. left C/N & called 7/18/00 1:55:45 PM
|
Pressure Test | 7/14/2000 | 7/14/2000 | 7/14/2000 | A | NR |
Carl Dependahl
|
|
|
To 350
|
Pressure Test | 7/13/2000 | 7/14/2000 | 7/14/2000 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 07/13/2000 at 16:06:36. Contact: ###-####.
|
Rough-in | 7/13/2000 | 7/14/2000 | 7/14/2000 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 07/13/2000 at 16:06:21. Contact: ###-####.
|