Final | 9/21/2000 | 9/21/2000 | 9/21/2000 | P | PASS |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 09/21/2000 at 09:46:20. Contact: ###-####.
|
Final | 9/19/2000 | 9/20/2000 | 9/20/2000 | A | FAIL |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 09/19/2000 at 12:21:14. Contact: ###-####. need hydronic permit and inspection 9/20/2000 10:56:39 AM
|
Pressure Test | 7/19/2000 | 7/20/2000 | 7/20/2000 | A | PASS |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 07/19/2000 at 13:13:51. Contact: ###-####.
|
Rough-in | 7/19/2000 | 7/20/2000 | 7/20/2000 | A | PASS |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 07/19/2000 at 13:13:31. Contact: ###-####.
|
Pressure Test | 7/12/2000 | 7/13/2000 | 7/13/2000 | A | FAIL |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 07/12/2000 at 12:00:46. Contact: ###-####.
|
Rough-in | 7/12/2000 | 7/13/2000 | 7/13/2000 | A | FAIL |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 07/12/2000 at 12:00:26. Contact: ###-####. C/N posted 7/13/00 1:40:03 PM
|