Final | 8/30/2000 | 8/31/2000 | 8/31/2000 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 08/30/2000 at 13:37:22. Contact: ###-####.
|
Pressure Test | 7/13/2000 | 7/13/2000 | 7/13/2000 | P | PASS |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 07/13/2000 at 08:36:09. Contact: ###-####.
|
Rough-in | 7/13/2000 | 7/13/2000 | 7/13/2000 | P | PASS |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 07/13/2000 at 08:35:49. Contact: ###-####.
|
Pressure Test | 7/12/2000 | 7/12/2000 | 7/12/2000 | P | FAIL |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 07/12/2000 at 10:11:10. Contact: ###-####.
|
Rough-in | 7/12/2000 | 7/12/2000 | 7/12/2000 | P | FAIL |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 07/12/2000 at 10:10:54. Contact: ###-####. C/N posted 7/13/00 11:23:46 AM
|