Final | 4/4/2001 | 4/4/2001 | 4/4/2001 | P | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 04/04/2001 at 09:12:05. Contact: ###-####.
|
Rough-in | 3/28/2001 | 3/28/2001 | 3/28/2001 | P | PASS |
Alan Hauser
|
|
|
ok for ceiling tile on south section 3/28/2001 2:14:06 PM
|
Final | 3/15/2001 | 3/15/2001 | 3/15/2001 | P | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 03/15/2001 at 11:06:02. Contact: ###-####.
partial final in office area still have unfinished ductwork..tom says hes waiting on materials..i told him to finish and then call 3/15/2001 1:22:03 PM
|
Rough-in | 2/28/2001 | 3/1/2001 | 3/1/2001 | P | PART |
Alan Hauser
|
|
|
duct only, no flex yet 3/1/2001 2:27:45 PM
|
Rough-in | 1/23/2001 | 1/23/2001 | 1/23/2001 | P | PART |
Alan Hauser
|
|
|
bathrooms only, ok 1/23/2001 3:12:34 PM
|