Final | 3/6/2001 | 3/7/2001 | 3/7/2001 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 03/06/2001 at 15:30:13. Contact: ###-####.
|
Final | 3/2/2001 | 3/2/2001 | 3/2/2001 | P | FAIL |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 03/02/2001 at 09:30:41. Contact: ###-####. vent clearance 3/2/2001 2:30:49 PM
|
Final | 3/2/2001 | 3/2/2001 | 3/2/2001 | P | FAIL |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 03/02/2001 at 09:30:41. Contact: ###-####. need vent clearance 3/2/2001 2:37:42 PM
|
Rough-in | 1/24/2001 | 1/24/2001 | 1/24/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 01/24/2001 at 08:27:20. Contact: ###-####.
|
Rough-in | 1/23/2001 | 1/23/2001 | 1/23/2001 | P | PART |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 01/23/2001 at 09:45:19. Contact: ###-####. r/i fail--no 90' offsets allowed in b-vent...b-vent to be 2' higher than vert wall within 8'---seal r/a plenum and out in garage 1/23/2001 3:03:34 PM
|