Final | 11/16/2001 | 11/16/2001 | 11/16/2001 | A | PASS |
Alan Hauser
|
|
|
Added by Inspector: 350 On 11/16/2001 11:17:35 AM
|
Final | 11/1/2001 | 11/7/2001 | 11/7/2001 | A | PASS |
Dave Lightfoot
|
|
|
###-#### AREA 5 AND 6 area 5 and 6 ok 11/6/2001 10:45:59 AM
|
Final | 10/29/2001 | 10/29/2001 | 10/29/2001 | P | CANC |
Dave Lightfoot
|
|
|
###-#### final on area 1-2 not right permit no. 10/29/2001 1:33:29 PM
|
Final | 10/5/2001 | 10/8/2001 | 10/8/2001 | A | PART |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 10/05/2001 at 08:19:17. Contact: ###-####.... 10/5/2001 1:06:13 PM east side of bldg36 meet bill at 8 10/5/2001 1:06:36 PM area 7 & 8 and 3 & 4 ok for final..area 1 & 2 ok for ceiling 10/8/2001 10:30:23 AM
|
Rough-in | 9/5/2001 | 9/7/2001 | 9/7/2001 | A | PART |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 09/05/2001 at 14:20:21. Contact: ###-####.
|
Rough-in | 8/14/2001 | 8/15/2001 | 8/15/2001 | A | PART |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 08/14/2001 at 15:40:56. Contact: ###-####. kitchen area not greese ducts 8/15/2001 12:55:54 PM
|
MEC-Aging Inspection | 8/6/2001 | 8/6/2001 | 8/6/2001 | | NR |
Dave Lightfoot
|
|
|
|
Rough-in | 5/30/2001 | 6/1/2001 | 6/1/2001 | A | PART |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 05/30/2001 at 15:06:39. Contact: ###-####. areas 3/4 up and down 5/31/2001 12:15:21 PM
|
Final | 5/22/2001 | 5/23/2001 | 5/23/2001 | A | NR |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 05/22/2001 at 13:59:38. Contact: ###-####. ok 5/23/2001 11:42:16 AM ok for ceiling cover areas 7 and 8 and upper 8 5/23/2001 11:44:03 AM
|
Rough-in | 4/10/2001 | 4/11/2001 | 4/11/2001 | A | PART |
Dave Lightfoot
|
|
|
###-#### bill fuller area 5 and 6 part. area 5 and 6 need all fire dampers installed 4/11/2001 11:56:59 AM
|
Conference | 4/3/2001 | 4/5/2001 | 4/5/2001 | A | CANC |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 04/03/2001 at 10:05:48. Contact: ###-####. gone on jury duty 4/6/2001 8:07:01 AM
|
Rough-in | 3/26/2001 | 3/27/2001 | 3/27/2001 | A | PART |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 03/26/2001 at 09:57:03. Contact: ###-####. area 7 and 8 2nd floor 3/27/2001 11:42:11 AM
|
Rough-in | 2/27/2001 | 2/28/2001 | 2/28/2001 | A | PART |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 02/27/2001 at 13:07:01. Contact: (208)
bill fuller ###-#### cell bldg 36 area 7-8 r/i 2/28/2001 11:34:08 AM
|