Final | 4/25/2001 | 4/26/2001 | 4/26/2001 | A | PASS |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 04/25/2001 at 17:08:10. Contact: ###-####.
|
Final | 4/17/2001 | 4/17/2001 | 4/17/2001 | P | FAIL |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 04/17/2001 at 09:11:59. Contact: ###-####. sleeve gas pipe through cement 4/17/2001 2:14:54 PM
|
Pressure Test | 2/23/2001 | 2/23/2001 | 2/23/2001 | P | PASS |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 02/23/2001 at 09:42:19. Contact: ###-####.
|
Rough-in | 2/22/2001 | 2/23/2001 | 2/23/2001 | A | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 02/22/2001 at 13:02:15. Contact: ###-####....bob--###-#### 2/23/2001 8:38:33 AM wrap pipe at found wall...test failed..no plans on site 2/23/2001 8:39:38 AM
|