Permit Information
Permit NumberMEC01-00859
StatusFinaled
Name ADVANCED HEATING/COOLING INC
Site Address 5081 N PARTAGAS ST
Project NameMACANUDO PLACE TOWNH
Customer Number 
ePlanReview 
Description
They need another pressure test even though it says passed as per Russ Owen they have not and will need another inspection... 3-30-01
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final5/11/20015/11/20015/11/2001PPASS
DetailsTony Young
Scheduled by a contractor via Hello! on 05/11/2001 at 11:05:22. Contact: ###-####.
Pressure Test4/2/20014/2/20014/2/2001PPASS
DetailsAlan Hauser
Scheduled by a contractor via Hello! on 04/02/2001 at 10:39:38. Contact: ###-####.
Pressure Test3/30/20014/2/20014/2/2001AFAIL
DetailsTony Young
###-####
Conference3/30/20013/30/20013/30/2001PCANC
DetailsRuss Owen
Added by Inspector: 407 On 3/30/2001 2:56:01 PM meet with contractor at site acorrection has been posted for failed gas test and has no record of a re-inspection,and no sticker on gas pipe, inspection records show 1 inspection only and indicates a pass this must be a mistake. also note at time of frame inspection 3/29/01 gauge was bellow test required and now flat 3/30/01. Told general contractor to have mechanical contractor re-test and recall inspection. 3/30/2001 3:11:39 PM
Conference3/30/20013/30/20013/30/2001PFAIL
DetailsRuss Owen
Added by Inspector: 407 On 3/30/2001 2:56:01 PM meet with contractor at site acorrection has been posted for failed gas test and has no record of a re-inspection,and no sticker on gas pipe, inspection records show 1 inspection only and indicates a pass this must be a mistake. also note at time of frame inspection 3/29/01 gauge was bellow test required and now flat 3/30/01. Told general contractor to have mechanical contractor re-test and recall inspection. 3/30/2001 3:11:39 PM
Pressure Test3/28/20013/28/20013/28/2001PPASS
DetailsDixie Fellows
Scheduled by a contractor via Hello! on 03/28/2001 at 08:44:18. Contact: ###-####.
Rough-in3/28/20013/28/20013/28/2001PPASS
DetailsDixie Fellows
Scheduled by a contractor via Hello! on 03/28/2001 at 08:43:54. Contact: ###-####.