Final | 9/13/2001 | 9/14/2001 | 9/14/2001 | A | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 09/13/2001 at 08:06:20. Contact: ###-####.
|
Rough-in | 8/27/2001 | 8/28/2001 | 8/28/2001 | A | PART |
Alan Hauser
|
|
|
still waiting for pvc pipe in r.a. plenum to be wrapped, no other corrections 8/28/2001 10:35:15 AM
|
Rough-in | 8/6/2001 | 8/7/2001 | 8/7/2001 | A | PART |
Alan Hauser
|
|
|
duct ok, correction on pvc piping in r.a. plenum above 1st floor ceiling 8/7/2001 11:22:03 AM
|
MEC-Aging Inspection | 7/10/2001 | 7/10/2001 | 7/10/2001 | | PASS |
Dixie Fellows
|
|
|
work in progress 7/10/2001 11:13:18 AM
|
Conference | 5/9/2001 | 5/10/2001 | 5/10/2001 | A | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 05/09/2001 at 11:27:17. Contact: ###-####.
|
Rough-in | 5/9/2001 | 5/10/2001 | 5/10/2001 | A | PART |
Alan Hauser
|
|
|
looked at ducts in shafts, ducts sealed ok 5/10/2001 10:37:08 AM
|