Pressure Test | 10/17/2001 | 10/18/2001 | 10/18/2001 | A | PASS |
Dixie Fellows
|
|
|
|
Final | 10/3/2001 | 10/4/2001 | 10/4/2001 | A | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 10/03/2001 at 15:24:50. Contact: ###-####....###-#### 10/4/2001 10:00:13 AM vent regulators 10' away from air intakes at rtu...gas flex connectors not sized correctly 10/4/2001 10:44:40 AM
|
Final | 10/4/2001 | 10/4/2001 | 10/4/2001 | P | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 10/04/2001 at 11:13:37. Contact: ###-####.
|
Pressure Test | 8/20/2001 | 8/20/2001 | 8/20/2001 | P | PART |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 08/20/2001 at 08:31:22. Contact: ###-####. MAIN LINE UP BLDG AND STUBBED AT ROOF OK.. 8/20/2001 3:05:30 PM
|
Rough-in | 8/16/2001 | 8/17/2001 | 8/17/2001 | A | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 08/16/2001 at 15:12:18. Contact: ###-####. gas test failed 8/17/2001 11:12:29 AM
|
Pressure Test | 6/18/2001 | 6/19/2001 | 6/19/2001 | A | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 06/18/2001 at 16:44:02. Contact: ###-####.
|
Pressure Test | 6/19/2001 | 6/19/2001 | 6/19/2001 | P | PASS |
Dixie Fellows
|
|
|
6/19/2001 9:54:26 AM
|