Final | 10/30/2001 | 10/30/2001 | 10/30/2001 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/30/2001 at 08:20:32. Contact: ###-####.
|
Rough-in | 10/3/2001 | 10/3/2001 | 10/3/2001 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/03/2001 at 10:42:31. Contact: ###-####. R/I and P/T previously passed.....No tag on pressure test. 10/3/2001 3:48:41 PM
|
Pressure Test | 9/28/2001 | 10/1/2001 | 10/1/2001 | P | PASS |
Alan Hauser
|
|
|
pres test--tml--###-####
|
Rough-in | 9/28/2001 | 10/1/2001 | 10/1/2001 | P | PASS |
Alan Hauser
|
|
|
tml ###-#### --r/i
|
Pressure Test | 9/28/2001 | 9/28/2001 | 9/28/2001 | P | CANC |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 09/28/2001 at 08:32:26. Contact: ###-####.cancel per veronica
|
Rough-in | 9/28/2001 | 9/28/2001 | 9/28/2001 | P | CANC |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 09/28/2001 at 08:32:18. Contact: ###-####.--cancel per veronica/mls
|