Final | 12/5/2001 | 12/6/2001 | 12/5/2001 | P | CANC |
Steven Webb
|
|
|
###-####
|
Final | 11/27/2001 | 11/28/2001 | 11/27/2001 | A | CANC |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 11/27/2001 at 11:34:06. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 11/27/2001 at 11:40:07.
|
Final | 11/27/2001 | 11/27/2001 | 11/27/2001 | P | PASS |
Dave Hannah
|
|
|
Added by Inspector: 425 On 11/27/2001 1:45:11 PM
|
Final | 11/26/2001 | 11/27/2001 | 11/27/2001 | A | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 11/26/2001 at 12:15:31. Contact: ###-####. condensate to terminate outside...connect gas line at f/p 11/27/2001 10:39:28 AM
|
Pressure Test | 10/9/2001 | 10/9/2001 | 10/9/2001 | P | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 10/09/2001 at 11:26:23. Contact: ###-####.
|
Rough-in | 10/9/2001 | 10/9/2001 | 10/9/2001 | P | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 10/09/2001 at 11:26:08. Contact: ###-####.
|