Final | 11/15/2001 | 11/16/2001 | 11/16/2001 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/15/2001 at 15:21:23. Contact: ###-####.
|
Rough-in | 10/26/2001 | 10/29/2001 | 10/29/2001 | A | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 10/26/2001 at 14:59:29. Contact: ###-####.
|
Rough-in | 10/25/2001 | 10/25/2001 | 10/25/2001 | P | FAIL |
Alan Hauser
|
|
|
correction notice posted 10/25/2001 3:19:36 PM
|
Conference | 10/24/2001 | 10/24/2001 | 10/24/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/24/2001 9:46:52 AM w/ dix...keep c/n, need reinsp.
|
Rough-in | 10/24/2001 | 10/24/2001 | 10/24/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/24/2001 5:14:02 PM c/n ok ...chk fresh air at final
|
Pressure Test | 10/22/2001 | 10/22/2001 | 10/22/2001 | P | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 10/22/2001 at 07:52:18. Contact: ###-####.
|
Rough-in | 10/22/2001 | 10/22/2001 | 10/22/2001 | P | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 10/22/2001 at 07:51:33. Contact: ###-####. supply duct to be strapped for support...not laying on wood 10/22/2001 2:29:27 PM
|