Final | 8/1/2002 | 8/1/2002 | 8/1/2002 | P | PASS |
Dixie Fellows
|
|
|
|
Final | 7/29/2002 | 7/30/2002 | 7/30/2002 | A | NR |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 07/29/2002 at 15:53:39. Contact: ###-####...emerald past mitchell before 5 mile 7/30/2002 8:21:06 AM
|
Pressure Test | 5/30/2002 | 5/31/2002 | 5/31/2002 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 05/30/2002 at 11:37:36. Contact: ###-####. hydronics for lieberts ok and holding 5/31/2002 10:40:55 AM
|
Pressure Test | 4/5/2002 | 4/8/2002 | 4/8/2002 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 04/05/2002 at 09:09:47. Contact: ###-####. 60" test and low test are both ok 4/8/2002 11:23:24 AM
|
MEC-Aging Inspection | 1/22/2002 | 1/22/2002 | 1/22/2002 | | PASS |
Dixie Fellows
|
|
|
WORK IN PROGRESS 1/22/2002 6:37:57 PM
|