Final | 1/23/2002 | 1/23/2002 | 1/23/2002 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 01/23/2002 at 10:12:39. Contact: ###-####...ok per411 1/23/2002 2:33:45 PM
|
Final | 1/21/2002 | 1/22/2002 | 1/22/2002 | P | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 01/21/2002 at 08:32:22. Contact: ###-####. no unions allowed in basement gas pipe...no access to furnace in crawl...to deep to jump 1/22/2002 5:19:19 PM
|
Final | 1/18/2002 | 1/22/2002 | 1/21/2002 | A | CANC |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 01/18/2002 at 08:31:35. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 01/21/2002 at 08:31:17.
|
Pressure Test | 11/8/2001 | 11/9/2001 | 11/9/2001 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/08/2001 at 15:42:11. Contact: ###-####. med press ok at 60# 11/9/2001 12:16:43 PM
|
Pressure Test | 11/7/2001 | 11/8/2001 | 11/8/2001 | A | FAIL |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 11/07/2001 at 11:08:01. Contact: ###-####. 60 psi test fail 11/8/2001 9:58:45 AM
|
Rough-in | 11/7/2001 | 11/8/2001 | 11/8/2001 | A | PASS |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 11/07/2001 at 11:08:25. Contact: ###-####.
|
Pressure Test | 11/6/2001 | 11/7/2001 | 11/7/2001 | A | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 11/06/2001 at 14:36:52. Contact: ###-####. 60# test failed 11/7/2001 11:15:57 AM
|
Rough-in | 11/6/2001 | 11/7/2001 | 11/7/2001 | A | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 11/06/2001 at 14:35:54. Contact: ###-####. frame chimney at 2nd floor
11/7/2001 11:16:34 AM
|
Rough-in | 11/5/2001 | 11/6/2001 | 11/6/2001 | A | PART |
Dixie Fellows
|
|
|
###-#### SAM r/i fail..med press gas failed..low pressure ok 11/6/2001 9:42:49 AM
|