Final | 12/19/2001 | 12/20/2001 | 12/20/2001 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 12/19/2001 at 16:48:32. Contact: ###-####.
|
Pressure Test | 11/14/2001 | 11/15/2001 | 11/15/2001 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 11/14/2001 at 14:22:36. Contact: ###-####.
|
Rough-in | 11/14/2001 | 11/15/2001 | 11/15/2001 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 11/14/2001 at 14:22:30. Contact: ###-####.
|
Pressure Test | 11/13/2001 | 11/14/2001 | 11/14/2001 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 11/13/2001 at 15:01:42. Contact: ###-####.
|
Rough-in | 11/13/2001 | 11/14/2001 | 11/14/2001 | A | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 11/13/2001 at 15:01:34. Contact: ###-####. need 1/4" mesh screen at f/a....strap bath exhaust every 4' vertically 11/14/2001 10:03:01 AM
|