Final | 6/6/2002 | 6/7/2002 | 6/7/2002 | P | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 06/06/2002 at 14:50:48. Contact: ###-####.
|
Final | 5/30/2002 | 5/31/2002 | 5/31/2002 | A | NR |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 05/30/2002 at 15:27:25. Contact: ###-####. conference on duct and f/a 5/31/2002 9:51:33 AM
|
Final | 5/30/2002 | 5/30/2002 | 5/30/2002 | P | NR |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 05/30/2002 at 08:18:53. Contact: ###-####.
|
Rough-in | 3/26/2002 | 3/27/2002 | 3/27/2002 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by Inspector: 411 On 3/26/2002 7:46:21 PM....FIRE DAMPERS IN ALL SUPPLY'S AND R/A GRILLES...CEILING ABOVE HOOD DONE...SHAFT OK...WILL NEED TO CHECK MAKE-UP AIR AND ROOF AT FINAL 3/27/2002 8:31:02 AM
|
Rough-in | 3/26/2002 | 3/26/2002 | 3/26/2002 | P | CANC |
Dixie Fellows
|
|
|
###-#### ###-####...###-#### carl 3/26/2002 4:11:07 PM
|
Conference | 2/8/2002 | 2/8/2002 | 2/8/2002 | P | PASS |
Alan Hauser
|
|
|
talked to carl, had owners contact health dept. for approval of galv. hood 2/8/2002 1:12:24 PM
|