Final | 7/31/2002 | 7/31/2002 | 7/31/2002 | P | PASS |
Alan Hauser
|
|
|
###-#### ALAN
|
Rough-in | 5/21/2002 | 5/22/2002 | 5/22/2002 | A | PASS |
Jim Storey
|
|
|
###-#### west end 6 units ok for cover. 5/22/2002 10:22:46 AM
|
Rough-in | 5/15/2002 | 5/15/2002 | 5/15/2002 | P | PART |
Alan Hauser
|
|
|
middle 6 ok for cover, makes 12 of 18 5/15/2002 2:06:18 PM
|
Rough-in | 5/8/2002 | 5/9/2002 | 5/9/2002 | A | PART |
Alan Hauser
|
|
|
only 6 5/9/2002 12:30:34 PM
|
Rough-in | 5/7/2002 | 5/7/2002 | 5/7/2002 | P | FAIL |
Alan Hauser
|
|
|
replace air connector with class 0 or 1 duct 5/7/2002 2:39:35 PM
|
Rough-in | 4/16/2002 | 4/16/2002 | 4/16/2002 | P | NR |
Alan Hauser
|
|
|
dryer vents to be within manufactures requirements, which are 3 elbows and 34 feet, place tag by dryer at final 4/16/2002 4:33:53 PM
|
Rough-in | 4/8/2002 | 4/8/2002 | 4/8/2002 | P | PART |
Dixie Fellows
|
|
|
###-#### ALAN waiting on engineer for dryer vent approval 4/9/2002 9:44:50 AM
|
Rough-in | 4/2/2002 | 4/3/2002 | 4/3/2002 | A | FAIL |
Dave Lightfoot
|
|
|
###-#### ALAN plans not on site 4/3/2002 9:45:50 AM
|
Rough-in | 3/28/2002 | 3/28/2002 | 3/28/2002 | P | PART |
Russ Owen
|
|
|
###-####. most all duct will need to be installed after sheetrock . 3/28/2002 4:20:50 PM it is bellow ceiling line. 3/28/2002 4:21:02 PM 3/28/2002 4:33:05 PM
|