Final | 6/25/2002 | 6/26/2002 | 6/26/2002 | A | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 06/25/2002 at 14:03:13. Contact: ###-####.
|
Final | 6/21/2002 | 6/24/2002 | 6/24/2002 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 06/21/2002 at 14:24:14. Contact: ###-####.
|
Final | 6/21/2002 | 6/24/2002 | 6/24/2002 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 06/21/2002 at 14:24:14. Contact: ###-####.c/n on site 6/24/2002 10:42:39 AM
|
Final | 6/21/2002 | 6/24/2002 | 6/24/2002 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 06/21/2002 at 14:24:14. Contact: ###-####.c/n on site 6/24/2002 10:42:39 AM
|
Final | 6/21/2002 | 6/24/2002 | 6/24/2002 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 06/21/2002 at 14:24:14. Contact: ###-####.c/n on site 6/24/2002 10:42:39 AM
|
Final | 6/21/2002 | 6/24/2002 | 6/24/2002 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 06/21/2002 at 14:24:14. Contact: ###-####.c/n on site 6/24/2002 10:42:39 AM
|
Pressure Test | 5/2/2002 | 5/2/2002 | 5/2/2002 | A | PASS |
Dave Hannah
|
|
|
Added by Inspector: 425 On 5/2/2002 9:04:24 AM
|
Rough-in | 5/1/2002 | 5/2/2002 | 5/2/2002 | A | PASS |
Dave Hannah
|
|
|
###-#### MERYL
|