Final | 7/24/2002 | 7/25/2002 | 7/25/2002 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 07/24/2002 at 11:18:28. Contact: ###-####.c/n items completed 7/25/2002 10:52:24 AM
|
Final | 7/23/2002 | 7/24/2002 | 7/24/2002 | A | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 07/23/2002 at 10:58:05. Contact: ###-####. need outside shutoff at f/p...no access to crawl 7/24/2002 10:04:11 AM
|
Pressure Test | 5/9/2002 | 5/10/2002 | 5/10/2002 | A | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 05/09/2002 at 13:02:44. Contact: ###-####.
|
Rough-in | 5/9/2002 | 5/10/2002 | 5/10/2002 | A | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 05/09/2002 at 13:02:20. Contact: ###-####.
|