Final | 10/9/2002 | 10/9/2002 | 10/9/2002 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/09/2002 at 07:20:40. Contact: ###-####.
|
Rough-in | 9/3/2002 | 9/4/2002 | 9/4/2002 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 09/03/2002 at 14:47:28. Contact: ###-####.
|
Pressure Test | 9/3/2002 | 9/3/2002 | 9/3/2002 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 09/03/2002 at 07:52:15. Contact: ###-####.
|
Rough-in | 9/3/2002 | 9/3/2002 | 9/3/2002 | P | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 09/03/2002 at 07:51:58. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 09/03/2002 at 08:43:10.
|
Rough-in | 9/3/2002 | 9/3/2002 | 9/3/2002 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 09/03/2002 at 07:51:58. Contact: ###-####.
|