Final | 12/26/2002 | 12/27/2002 | 12/27/2002 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 12/26/2002 at 10:34:46. Contact: ###-####. no card on site..microfished engineer change in crawl for ductwork...with plans 12/27/2002 9:33:04 AM
|
Rough-in | 12/3/2002 | 12/4/2002 | 12/4/2002 | A | PART |
Dixie Fellows
|
|
|
rick ###-#### 12/3/2002 7:06:22 PM ok to sheetrock equip room...dave with musgrove faxing new drawings for crawl 12/4/2002 9:19:51 AM
|
Rough-in | 12/2/2002 | 12/3/2002 | 12/3/2002 | A | CANC |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 12/02/2002 at 18:02:10. Contact: ###-####. will reschedule 12/3/2002 7:06:33 PM
|
Rough-in | 11/19/2002 | 11/19/2002 | 11/19/2002 | A | PART |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 11/19/2002 at 07:22:29. Contact: ###-####. r/i and gas ok..need ok from engineer by final about change in ducts in crawl 11/19/2002 9:24:21 AM
|
Rough-in | 11/15/2002 | 11/18/2002 | 11/18/2002 | A | FAIL |
Dixie Fellows
|
|
|
posted corr..talked with cont 11/18/2002 9:26:29 AM
|
Rough-in | 11/15/2002 | 11/15/2002 | 11/15/2002 | P | CANC |
Dixie Fellows
|
|
|
###-#### shaun will reschedule...meet shaun at 8:30 mon am 11/15/2002 3:39:36 PM
|