Permit Information
Permit NumberMEC03-01155
StatusFinaled
Name YMC INC
Site Address 7200 W BARRISTER DR
Project NameAda County Jail
Customer Number21311
ePlanReview 
Description
POD C HOUSING ADDITION.. COMPLETE HVAC ...PER INITIAL CERT OF VALUE $ 645.000.00 // Final value $615,000. adh.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  3/18/2004 DONE
Final3/11/20043/11/20043/11/2004PPASS
DetailsTroy James
Final3/2/20043/3/20043/3/2004APART
DetailsTroy James
Phone #: ###-#### Internet Inspection Request from: Rhonda Marcum
Final3/2/20043/3/20043/3/2004PPART
DetailsTroy James
don; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
Pressure Test2/11/20042/12/20042/12/2004APASS
DetailsDixie Fellows
donny; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie 100lb test on hydronics ok...all pipe tested 2/12/2004 10:35:18 AM
Pressure Test2/11/20042/11/20042/11/2004PFAIL
DetailsDixie Fellows
donny; Phone #: ###-#### Internet Inspection Request from: Darla Downs guage pegged 2/11/2004 1:51:21 PM
Rough-in2/10/20042/10/20042/10/2004PPASS
DetailsDixie Fellows
Scheduled by a contractor via Hello! on 2/10/2004 at 7:49:45 AM. Contact: ###-####. 100LB HYDRONIC FOR HEAT OK 2/10/2004 2:55:15 PM
Pressure Test2/9/20042/9/20042/9/2004PPASS
DetailsDixie Fellows
don; Phone #: ###-#### Internet Inspection Request from: Annette Moore 60LB GAS TEST IN MECH ROOM OK //411
Rough-in12/9/200312/10/200312/10/2003APART
DetailsDixie Fellows
Scheduled by a contractor via Hello! on 12/9/2003 at 1:13:47 PM. Contact: ###-####...ok to cover all lids up to mech room 12/10/2003 9:45:17 AM
Rough-in12/9/200312/10/200312/10/2003APART
DetailsDixie Fellows
Don; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes 100lb hydronic test and 60lb main gas to mech room ok 12/10/2003 9:45:48 AM
Rough-in12/9/200312/9/200312/9/2003PFAIL
DetailsDixie Fellows
don; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
Rough-in10/21/200310/24/200310/24/2003APART
DetailsDixie Fellows
Scheduled by a contractor via Hello! on 10/21/2003 at 8:31:51 AM. Contact: ###-####. walk-through with brad and looked at layout..no s.f dampers, etc installed yet 10/24/2003 9:47:28 AM
Conference9/18/20039/19/20039/19/2003APASS
DetailsDixie Fellows
Phone #: ###-#### Internet Inspection Request from: Rhonda Marcum
MEC-Aging Inspection9/1/20039/1/20039/1/2003 PASS
DetailsDixie Fellows
work in progress 9/2/2003 8:01:36 AM
Pressure Test7/1/20037/1/20037/1/2003PPART
DetailsAlan Hauser
tested only piping on old roof, where pipe goes from 10# and splits into two 5# lines, one for old bldg. and one will extend over into new bldg. 7/1/2003 11:41:57 PM
Conference6/19/20036/20/20036/20/2003APASS
DetailsDixie Fellows
don ###-####
Conference6/19/20036/19/20036/19/2003PNR
DetailsDixie Fellows
###-#### don will meet don fri am..reschedled 6/19/2003 3:53:52 PM