Final | 3/14/2005 | 3/14/2005 | 3/14/2005 | P | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 3/14/2005 at 9:12:00 AM. Contact: ###-####.
|
Final | 3/10/2005 | 3/11/2005 | 3/11/2005 | A | PART |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 3/10/2005 at 12:42:06 PM. Contact: ###-####. comb air to w/h not interlocked 3/11/2005 10:09:23 AM
|
Final | 3/9/2005 | 3/10/2005 | 3/10/2005 | A | NR |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 3/9/2005 at 12:31:48 PM. Contact: ###-####.
|
Rough-in | 3/8/2005 | 3/8/2005 | 3/8/2005 | P | NR |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 3/8/2005 at 9:15:14 AM. Contact: ###-####.
|
Final | 3/4/2005 | 3/7/2005 | 3/7/2005 | P | NR |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 3/4/2005 at 3:44:39 PM. Contact: ###-####. walked job with ben and discussed corrections 3/7/2005 2:21:48 PM
|
Rough-in | 2/24/2005 | 2/25/2005 | 2/25/2005 | A | PART |
Dixie Fellows
|
|
|
meet mike at 8:30...###-#### did walk through with mike..wrote list of items to be completed before final 2/25/2005 10:34:28 AM
|
Rough-in | 2/23/2005 | 2/24/2005 | 2/24/2005 | P | NH |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 2/23/2005 at 12:11:41 PM. Contact: ###-####....unable to meet mike..i rescheduled this for fri am 2/24/2005 4:47:56 PM
|
Final | 1/13/2005 | 1/18/2005 | 1/18/2005 | P | NR |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 1/13/2005 at 3:30:55 PM. Contact: ###-####. this was for a conference regarding type 1 hood 1/18/2005 1:31:00 PM
|
Rough-in | 11/22/2004 | 11/23/2004 | 11/23/2004 | P | PART |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 11/22/2004 at 2:18:11 PM. Contact: ###-####. complete r/i ok on 3rd and 4th floors 11/23/2004 3:11:28 PM
|
Rough-in | 9/28/2004 | 9/28/2004 | 9/28/2004 | P | PART |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 9/28/2004 at 8:43:30 AM. Contact: ###-####. f/p's and line-sets on first floor ok 9/28/2004 2:21:35 PM
|
Rough-in | 9/10/2004 | 9/13/2004 | 9/13/2004 | A | PART |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 9/10/2004 at 8:44:10 AM. Contact: ###-####. ok to cover 1st and 2nd floors..will check f/p on next inspection 9/13/2004 1:41:29 PM
|
Rough-in | 8/16/2004 | 8/18/2004 | 8/18/2004 | A | FAIL |
Alan Hauser
|
|
|
1st flr. bath exhaust fans, pipe lapped wrong way. need installation for house dryers for exhaust clearance and combustion air requirements 8/18/2004 11:57:58 AM
|
Conference | 6/22/2004 | 6/29/2004 | 6/29/2004 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 6/22/2004 at 3:10:02 PM. Contact: ###-#### meeting at 9:00am reviewed plans and discussed job, etc 6/29/2004 9:28:53 AM
|