Final | 11/8/2005 | 11/9/2005 | 11/9/2005 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 11/8/2005 at 9:48:32 AM. Contact: ###-####.
|
Rough-in | 11/2/2005 | 11/3/2005 | 11/3/2005 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 11/2/2005 at 11:23:30 AM. Contact: ###-####...all questions from correction have been answered..waiting on last connection of comb air into dryers..there will be protection at outside unit at final
|
Rough-in | 10/31/2005 | 10/31/2005 | 10/31/2005 | A | FAIL |
Dixie Fellows
|
|
|
need engineering on dryer vent..combustion air or make-up air? who is permitting the dryers? they will have to be added to the permit
|