Final | 9/26/2006 | 9/26/2006 | 9/26/2006 | P | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 9/26/2006 at 8:08:32 AM. Contact: ###-####.
|
MEC-Aging Inspection | 8/1/2006 | 8/1/2006 | 8/2/2006 | | PASS |
Dixie Fellows
|
|
|
called g/c...work in progress
|
Pressure Test | 5/31/2006 | 6/1/2006 | 6/1/2006 | A | PART |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 5/31/2006 at 2:37:48 PM. Contact: ###-####....60lb test to gas ok...100lb test on chill ok
|
Pressure Test | 5/30/2006 | 5/31/2006 | 5/31/2006 | A | PART |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 5/30/2006 at 2:33:21 PM. Contact: ###-####....main chillers 100lb ok
|
Pressure Test | 5/23/2006 | 5/23/2006 | 5/23/2006 | P | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 5/23/2006 at 8:53:30 AM. Contact: ###-####...100lb test on hydronic heating loop for main supply and returns ok
|
Pressure Test | 5/4/2006 | 5/4/2006 | 5/4/2006 | A | PART |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 5/4/2006 at 7:26:14 AM. Contact: ###-####....3rd floor hydronic loop for heat ok
|
Pressure Test | 4/27/2006 | 4/27/2006 | 4/27/2006 | P | PART |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 4/27/2006 at 9:57:39 AM. Contact: ###-####....100lb test on hydronic heat for 2nd floor ok
|
Pressure Test | 4/20/2006 | 4/21/2006 | 4/21/2006 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 4/20/2006 at 2:50:46 PM. Contact: ###-####....100lb hydronic for 1st floor heat loop ok
|
MEC-Aging Inspection | 4/14/2006 | 4/14/2006 | 4/19/2006 | | PASS |
Dixie Fellows
|
|
|
wip
|