Final | 2/26/2007 | 2/26/2007 | 2/26/2007 | P | PASS |
Dixie Fellows
|
|
|
Dixie, I want to get a final on the rough in only. I''m going to hold off on completing it until possibly late this year or perhaps not at all depending on how the existing system performs. I had a conference with Tony and he suggested that you could final it so he can issue the CO. Please call before stopping by so I can make sure to be there.
Thanks! Jim Phone #: ###-####
|
Rough-in | 6/28/2006 | 6/30/2006 | 6/30/2006 | A | PART |
Dixie Fellows
|
|
|
Inspection for radiant floor heat. Concrete is scheduled for 11:00, please advise if inspection cannot be completed before the pour. Thanks Dixie! ; Phone #: ..test###-#### Internet Inspection ...Request from: Jim Ritter..test on loop ok
|
Rough-in | 6/28/2006 | 6/29/2006 | 6/28/2006 | A | CANC |
Dixie Fellows
|
|
|
jim Note: for layout and pictures prior to pour; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Inspection cancelled from web by: Jim Ritter
|