Final | 10/16/2006 | 10/17/2006 | 10/17/2006 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 10/16/2006 at 3:38:21 PM. Contact: ###-####.
|
Rough-in | 10/12/2006 | 10/12/2006 | 10/12/2006 | P | PASS |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 10/12/2006 at 11:01:25 AM. Contact: ###-####. ok venting of boiler
|
Pressure Test | 7/26/2006 | 7/27/2006 | 7/27/2006 | A | PART |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 7/26/2006 at 2:54:07 PM. Contact: ###-####....100lb test on hydronics basement ok
|
Rough-in | 7/25/2006 | 7/25/2006 | 7/25/2006 | P | PART |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 7/25/2006 at 11:23:21 AM. Contact: ###-####....ok to cover bathrooms
|
Rough-in | 7/13/2006 | 7/13/2006 | 7/14/2006 | P | NR |
Alan Hauser
|
|
|
contact inspector for this area and see if this was done
|
Rough-in | 7/7/2006 | 7/10/2006 | 7/10/2006 | A | PART |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 7/7/2006 at 6:23:30 PM. Contact: ###-####...ok to partial cover..talked with tony and contractor and he will recall when correct duct is installed..grovers sold him the metal accordian flex duct
|
Conference | 6/26/2006 | 6/27/2006 | 6/27/2006 | A | PASS |
Dixie Fellows
|
|
|
mike ###-####..met with mike and discussed the venting on his boiler in the basement based on the manuf specs
|
Conference | 6/26/2006 | 6/26/2006 | 6/26/2006 | P | NR |
Dixie Fellows
|
|
|
###-#### mike..rescheduled for tues
|