Final | 2/19/2008 | 2/20/2008 | 2/20/2008 | A | PASS |
Bill VanDegrift
|
|
|
need all three floors finaled. needs to have a thread to the BLD-07-02244 permit that was pulled out on a 3rd floor T.I. so Boise cascade can get occupancy in that area. Call Mike ###-#### Internet Inspection Request from: Greg Fannin signed card
|
Final | 2/18/2008 | 2/19/2008 | 2/19/2008 | A | FAIL |
Dixie Fellows
|
|
|
Need final for all areas of 1st,2nd and 3rd floors,problem with permit boise cascade took out for part of 3rd floor not linked to this permit and he cannot get his occupancy. See Mike at ###-#### to resolve this. Phone #: ###-#### Internet Inspection Request from: Greg Fannin...no card on site
|
Rough-in | 12/20/2007 | 12/21/2007 | 12/21/2007 | A | PASS |
Troy James
|
|
|
Need rough in for 3rd floor southwest. Call Mike at ###-#### Phone #: ###-#### Internet Inspection Request from: Greg Fannin
|
Rough-in | 11/23/2007 | 11/26/2007 | 11/26/2007 | A | PASS |
Troy James
|
|
|
need inspection for 3rd floor NW. Call Mike ###-#### Phone #: ###-#### Internet Inspection Request from: Greg Fannin
|
Rough-in | 10/24/2007 | 10/25/2007 | 10/25/2007 | A | PART |
Troy James
|
|
|
need rough in for 3rd floor NE quad. Call Mike ###-#### Phone #: ###-#### Internet Inspection Request from: Greg Fannin ok to cover
|
Rough-in | 10/5/2007 | 10/8/2007 | 10/8/2007 | A | PASS |
Dixie Fellows
|
|
|
need rough in for 3rd floor south east quad. Call Mike ###-#### Phone #: ###-#### Internet Inspection Request from: Greg Fannin
|
MEC-Aging Inspection | 9/26/2007 | 9/26/2007 | 9/26/2007 | | PASS |
Dixie Fellows
|
|
|
wip
|
Final | 7/20/2007 | 7/23/2007 | 7/23/2007 | A | PASS |
Dixie Fellows
|
|
|
Need final for Audio Visual room on first floor . Mike ###-#### Phone #: ###-#### Internet Inspection Request from: Greg Fannin
|
Rough-in | 7/20/2007 | 7/23/2007 | 7/23/2007 | A | PASS |
Dixie Fellows
|
|
|
Need rough in for 1st floor South west quadrant. Mike ###-#### Phone #: ###-#### Internet Inspection Request from: Greg Fannin
|
Rough-in | 6/20/2007 | 6/21/2007 | 6/21/2007 | A | PASS |
Dixie Fellows
|
|
|
need rough in for 1st floor northwest 2nd half rough in. Mike ###-#### Phone #: ###-#### Internet Inspection Request from: Greg Fannin
|
Rough-in | 6/5/2007 | 6/5/2007 | 6/6/2007 | P | PART |
Dixie Fellows
|
|
|
jamie - 1st floor 1/2 of quad 3; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
Rough-in | 5/11/2007 | 5/11/2007 | 5/11/2007 | A | PART |
Dixie Fellows
|
|
|
need rough in for 1st floor NE quad. See mike. ###-#### Phone #: ###-#### Internet Inspection Request from: Greg Fannin..ok to cover this section
|
Rough-in | 4/25/2007 | 4/26/2007 | 4/26/2007 | A | PART |
Dixie Fellows
|
|
|
need rough in for 1st floor SE quadrant. Mike ###-#### Phone #: ###-#### Internet Inspection Request from: Greg Fannin...###-####
|
Rough-in | 3/15/2007 | 3/16/2007 | 3/16/2007 | A | PART |
Dixie Fellows
|
|
|
Need inspection of fire wrap on stairwell ventilation duct. Call Kelly of trinity insulation ###-#### to arrange to meet him at jobsite Phone #: ###-####...all fire wrap on stairwell ducts ok..nice job
|
Rough-in | 1/10/2007 | 1/12/2007 | 1/12/2007 | A | PART |
Dixie Fellows
|
|
|
Need rough in on penthouse fans meet mike ###-#### Phone #: ###-####..looked at fans and discussed fire wrap issues, etc..did the engineer call for detectors?
|
Rough-in | 11/20/2006 | 11/21/2006 | 11/21/2006 | A | PASS |
Dixie Fellows
|
|
|
Need rough in for cover on 2nd floor SW corner. Call Mike at ###-####; Phone #: ###-#### Internet Inspection Request from: Greg Fannin...some existing duct not approved by this code was used..(air connector)
|
Rough-in | 10/26/2006 | 10/27/2006 | 10/27/2006 | A | PART |
Dixie Fellows
|
|
|
ok to cover this section
|
Rough-in | 10/25/2006 | 10/26/2006 | 10/26/2006 | A | CANC |
Dixie Fellows
|
|
|
need partial rough-in for 2nd floor 3rd core. Mike ###-####; Phone #: ###-#### Internet Inspection Request from: Greg Fannin
|
Rough-in | 10/2/2006 | 10/3/2006 | 10/3/2006 | A | PART |
Dixie Fellows
|
|
|
###-####..OK TO COVER THIS SECTION
|
Rough-in | 9/29/2006 | 10/2/2006 | 10/2/2006 | A | PEND |
Dixie Fellows
|
|
|
Need partial roughin for cover. 2nd floor NE quadrant. Please call Mike ###-#### ; Phone #: ###-#### Internet Inspection Request from: Greg Fannin..unable to meet up with mike today..i called him and told him i rescheduled this for tues am..thanks
|
Rough-in | 9/14/2006 | 9/15/2006 | 9/15/2006 | A | PART |
Dixie Fellows
|
|
|
###-#### mike..ok to cover this section
|
Rough-in | 9/14/2006 | 9/14/2006 | 9/14/2006 | A | CANC |
Dixie Fellows
|
|
|
###-#### mike..out of time so i rescheduled this for fri am..thanks dixie
|
Conference | 9/13/2006 | 9/14/2006 | 9/14/2006 | A | PASS |
Dixie Fellows
|
|
|
need partial final on second floor S.E. corner. Please call Mike at ###-#### and he will meet you.; Phone #: ###-#### Internet Inspection Request from: Greg Fannin..this should have been scheduled for a r/i, so i sent it back to myself for one. dixie
|
Rough-in | 9/11/2006 | 9/12/2006 | 9/12/2006 | A | FAIL |
Dixie Fellows
|
|
|
Need partial cover on 2nd floor S.E. quadrant. Please call Mike at ###-#### to schedule meeting him at the jobsite.; Phone #: ###-#### Internet Inspection Request from: Greg Fannin..talked to mike about cleaning up flex duct drops into diffusers as per manuf specs..he will recall when ready
|