Final | 1/25/2007 | 1/26/2007 | 1/26/2007 | A | PASS |
Bill VanDegrift
|
|
|
Please do mechanical final inspection. There is a key above the exterior light at unit 102 that fits all of unit''s doors. Thank You! Phone #: ###-####
|
Rough-in | 11/28/2006 | 11/28/2006 | 11/28/2006 | P | PASS |
Troy James
|
|
|
Please do mechanical rough in reinspection. Corrected 1" clearance on flu shields. Thank You!; Phone #: ###-#### Internet Inspection Request from: Donnette Ellis
|
Rough-in | 11/27/2006 | 11/27/2006 | 11/27/2006 | P | FAIL |
Troy James
|
|
|
Please do gas pressure test with mechanical rough in reinspection. Thank you!; Phone #: ###-#### Internet Inspection Request from: Donnette Ellis maintain 1" clearance around flue with insulation shield, pressure test ok
|
Conference | 11/21/2006 | 11/22/2006 | 11/22/2006 | A | CANC |
Troy James
|
|
|
Can you please meet for conference at 8:00 am Wed. morning with Keith from Ellis Heating and the builder? Thank You!; Phone #: ###-#### Internet Inspection Request from: Donnette Ellis canc per donnette over phone
|
Rough-in | 11/21/2006 | 11/21/2006 | 11/21/2006 | P | FAIL |
Troy James
|
|
|
Please do gas pressure witness test with mechanical rough in inspection. Thank You!; Phone #: ###-#### Internet Inspection Request from: Donnette Ellis c/n posted front window
|
Rough-in | 10/31/2006 | 10/31/2006 | 10/31/2006 | P | FAIL |
Alan Hauser
|
|
|
not ready, gaslines are buried, dryer exhaust is outside walls, no access to upstairs, and how many sq. inches are the combustion air openings rated at.
|