Final | 12/12/2006 | 12/12/2006 | 12/12/2006 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 12/12/2006 at 6:38:16 AM. Contact: ###-####...corrections made on s/f dampers
|
Final | 12/8/2006 | 12/8/2006 | 12/8/2006 | A | PEND |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 12/8/2006 at 6:58:11 AM. Contact: ###-####...mark will reschedule for mondayt am
|
Rough-in | 11/16/2006 | 11/20/2006 | 11/20/2006 | A | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 11/16/2006 at 6:46:23 AM. Contact: ###-####...s/f dampers not installed correctly..talked with mark and troy
|
Rough-in | 11/8/2006 | 11/8/2006 | 11/8/2006 | A | PART |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 11/8/2006 at 6:49:54 AM. Contact: ###-####....s/f dampers in shaft A-ok..
|
Rough-in | 11/7/2006 | 11/7/2006 | 11/7/2006 | A | NR |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 11/7/2006 at 6:11:56 AM. Contact: ###-####...i was unable to make it this am..i called mark and had him reschedule for wed am..ok with g/c as well..thanks alot dixie
|