Final | 6/15/2007 | 6/18/2007 | 6/18/2007 | A | DONE |
Dixie Fellows
|
|
|
Harris, ###-#### - rocks are now in place that you wanted to look at in the burners
|
Final | 5/23/2007 | 5/23/2007 | 5/23/2007 | A | PASS |
Dixie Fellows
|
|
|
|
Pressure Test | 4/4/2007 | 4/4/2007 | 4/5/2007 | P | PART |
Dixie Fellows
|
|
|
Ben whole bld is ready; Phone #: ###-#### Internet Inspection Request from: Stacie Backus...gas from meter to equipment 20lb test ok..entire length of existing gas has been tested...dixie
|
Pressure Test | 4/2/2007 | 4/3/2007 | 4/3/2007 | A | PART |
Dixie Fellows
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Victoria Beall..20lb test inside w/h bldg to u/g fire=pits ok..about 20'
|
Pressure Test | 3/29/2007 | 3/29/2007 | 3/29/2007 | P | PART |
Dixie Fellows
|
|
|
brian; Phone #: ###-#### Internet Inspection Request from: Victoria Beall...3-20lb tests to fire-pits ok (u/g)
|
Pressure Test | 3/23/2007 | 3/26/2007 | 3/26/2007 | A | FAIL |
Dixie Fellows
|
|
|
Brian; Phone #: ###-#### Internet Inspection Request from: Stacie Backus..need letter from engineer for fire-pit locations (3)....test holding so i will tag after i receive the information..dixie
|
Pressure Test | 3/21/2007 | 3/22/2007 | 3/22/2007 | A | FAIL |
Dixie Fellows
|
|
|
Todd; Phone #: ###-#### Internet Inspection Request from: Stacie Backus..need btu load for fire pit..sleeve gas line u/g at concrete wall..need certificate for installing plastic pipe..will require a drawing of the fire-pits
|