Final | 1/7/2008 | 1/7/2008 | 1/7/2008 | P | PASS |
Alan Hauser
|
|
|
|
Pressure Test | 12/26/2007 | 12/27/2007 | 12/27/2007 | A | PASS |
Alan Hauser
|
|
|
|
Final | 12/21/2007 | 12/24/2007 | 12/24/2007 | A | PART |
Alan Hauser
|
|
|
all areas ok for cover, only gas piping left to look at
|
Final | 12/11/2007 | 12/12/2007 | 12/12/2007 | A | PART |
Troy James
|
|
|
John Hodgin is the field contact. We need a partial final inspection for above ceiling. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet ok areas 1 and 2 first floor, need to complete angles on fsd second floor
|
Final | 11/19/2007 | 11/21/2007 | 11/21/2007 | P | PART |
Alan Hauser
|
|
|
John Hodgin is the field contact. Partial Final inspection in area 1 on 1st and 2nd floor. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet
|
Pressure Test | 11/8/2007 | 11/9/2007 | 11/9/2007 | P | PASS |
Alan Hauser
|
|
|
60# test on gasline for whole system, and test on hydronics for all 1st floor
|
Rough-in | 10/25/2007 | 10/26/2007 | 10/26/2007 | A | PART |
Alan Hauser
|
|
|
all of building looked at, except mh112, still need gas piping looked at
|
Rough-in | 9/14/2007 | 9/17/2007 | 9/17/2007 | P | PART |
Alan Hauser
|
|
|
duct ok for 2nd floor south west wing
|
Rough-in | 9/7/2007 | 9/10/2007 | 9/10/2007 | P | PART |
Alan Hauser
|
|
|
area 3 and 4 lst floor duct ok, still have dampers to install
|
Conference | 8/22/2007 | 8/22/2007 | 8/22/2007 | P | PASS |
Alan Hauser
|
|
|
talked about roof curbs
|