Final | 3/9/2010 | 3/9/2010 | 3/9/2010 | A | PASS |
Troy James
|
|
|
gas piping completed to all rtu, unit heaters and water heater forgot to clock time, need to show 30min
|
Pressure Test | 2/22/2010 | 2/22/2010 | 2/22/2010 | P | PASS |
Troy James
|
|
|
ok gas piping on roof that was previously installed by another contractor back to gas meter
|
MEC-Aging Inspection | 2/11/2010 | 2/11/2010 | 2/11/2010 | | CANC |
Troy James
|
|
|
|
Pressure Test | 2/11/2010 | 2/11/2010 | 2/11/2010 | A | PASS |
Troy James
|
|
|
60# test ok to gas piping as shown on plans, need to have test done to 2" gas piping from meter, 2" gas pipe was installed by another contractor but will be inspected under this permit
|