Final | 7/1/2010 | 7/1/2010 | 7/1/2010 | P | PASS |
Dixie Fellows
|
|
|
meridian plumbing
|
Final | 6/28/2010 | 6/30/2010 | 6/30/2010 | A | PEND |
Dixie Fellows
|
|
|
glenn ###-####...rescheduled for thurs am
|
Conference | 6/25/2010 | 6/28/2010 | 6/28/2010 | A | PASS |
Dixie Fellows
|
|
|
call Glenn and discuss make-up air and CDHD...discussed change of occupancy
|
Final | 6/24/2010 | 6/25/2010 | 6/25/2010 | A | PEND |
Dixie Fellows
|
|
|
9:00 MEET GLENN ###-####...ok to run pizza oven..we will meet monday and i will get the letter stating the oven will be used for bread only
|
Final | 6/23/2010 | 6/24/2010 | 6/24/2010 | P | PEND |
Dixie Fellows
|
|
|
Job contact is Glen Wallace with Steamco, ###-####. Inspection requested from web by: Chris Field Phone #: ###-####..RESCHEDULED FOR FRI AM
|