Final | 6/14/2011 | 6/14/2011 | 6/14/2011 | P | PASS |
Dixie Fellows
|
|
|
oleg Phone #: ###-####
|
Final | 6/10/2011 | 6/10/2011 | 6/10/2011 | P | FAIL |
Dixie Fellows
|
|
|
oleg Phone #: ###-####....unable to find air-balance report...need upper and lower comb air minimum 100" opening each at furnace
|
Final | 6/8/2011 | 6/9/2011 | 6/9/2011 | A | FAIL |
Dixie Fellows
|
|
|
Oleg Phone #: ###-####...air blance not done yet
|
Rough-in | 4/26/2011 | 4/26/2011 | 4/26/2011 | P | PASS |
Dixie Fellows
|
|
|
Oleg Phone #: ###-####...r/i and 20lb gas ok...duct blaster test was already done and posted on furnace...i told oleg from now on we needed to witness it
|
Rough-in | 4/21/2011 | 4/21/2011 | 4/21/2011 | P | FAIL |
Dixie Fellows
|
|
|
Ollie Phone #: ###-####..need stamped approved wright soft plans on site
|
Rough-in | 4/20/2011 | 4/20/2011 | 4/20/2011 | P | FAIL |
Dixie Fellows
|
|
|
oleg - fireplace inspection Phone #: ###-####...wrong wright soft paper work on site
|
Pressure Test | 4/15/2011 | 4/18/2011 | 4/18/2011 | A | PASS |
Bill VanDegrift
|
|
|
Ollie-rough in and pressure test please Phone #: ###-#### 20# gas test only ok
|