Final | 7/22/2011 | 7/22/2011 | 7/22/2011 | P | PASS |
Dixie Fellows
|
|
|
>> Inspection requested via web by Stephanie Brown
|
Rough-in | 6/28/2011 | 6/28/2011 | 6/28/2011 | A | PASS |
Eric Strole
|
|
|
scott - ###-#### - r.i and blasting witness -rough-in pass, duct blast test pass, 20 lb gas test pass.
|
Rough-in | 6/27/2011 | 6/28/2011 | 6/28/2011 | A | PEND |
Dixie Fellows
|
|
|
Please schedule ri inspection along with the blasting witness for 9am Tuesday morning. Scott will meet you on the jobsite ###-####. >> Inspection requested via web by Stephanie Brown...scott rescheduled for wed am at 11:00
|
Rough-in | 6/23/2011 | 6/24/2011 | 6/24/2011 | P | NR |
Dixie Fellows
|
|
|
>> Inspection requested via web by Stephanie Brown....will reschedule the same day at duct blaster test
|
Rough-in | 6/22/2011 | 6/23/2011 | 6/23/2011 | P | CANC |
Dixie Fellows
|
|
|
>> Inspection requested via web by Stephanie Brown Inspection cancelled from web by: Stephanie Brown
|