Final | 9/6/2011 | 9/7/2011 | 9/7/2011 | A | PASS |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Debbie Marino
|
Rough-in | 7/18/2011 | 7/18/2011 | 7/18/2011 | P | PASS |
Eric Strole
|
|
|
coil to be replaced by final
|
Pressure Test | 7/15/2011 | 7/18/2011 | 7/18/2011 | A | PASS |
Eric Strole
|
|
|
Building Energy will perform duct blast test at 11 am on 7/18/11. Phone #: ###-#### >> Inspection requested via web by Debbie Marino-20 lb test pass
|
Rough-in | 7/15/2011 | 7/18/2011 | 7/18/2011 | A | FAIL |
Eric Strole
|
|
|
Building Energy will perform duct blast test at 11 am on 7/18/11. Phone #: ###-#### >> Inspection requested via web by Debbie Marino-duct blast pass, coil is over sized & needs to be per manual j report.
|