Final | 9/8/2011 | 9/9/2011 | 9/9/2011 | A | PASS |
Troy James
|
|
|
10:30am meet with geoff and shaun
|
Final | 9/8/2011 | 9/8/2011 | 9/8/2011 | P | FAIL |
Troy James
|
|
|
Recieved a call from the builder saying no inspector, need final inspection, both airbalance and duct blast are done and report is on dite with man J >> Inspection requested via web by Shaun Vogler installed 2 ton heat pump, design calls for 1.5 ton
|
Final | 9/7/2011 | 9/7/2011 | 9/7/2011 | P | CANC |
Dixie Fellows
|
|
|
meet jeff at 3:45 for duct blaster and air balance...sent to troy
|
Final | 9/7/2011 | 9/7/2011 | 9/7/2011 | A | NR |
Dixie Fellows
|
|
|
I will be on site for the final along with the air balance company at 10:00. Phone #: ###-#### >> Inspection requested via web by Shaun Vogler...rescheduled to meet jeff at 3:45
|
Final | 9/1/2011 | 9/1/2011 | 9/1/2011 | P | FAIL |
Troy James
|
|
|
Shaun Phone #: ###-#### not ready, no duct blast test or air balance test
|
Rough-in | 7/20/2011 | 7/20/2011 | 7/20/2011 | A | PASS |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Shaun Vogler-rough-in pass, no furnace at this time & no duct blast test.
|