Final | 3/2/2012 | 3/5/2012 | 3/5/2012 | A | PASS |
Alan Hauser
|
|
|
|
Final | 2/14/2012 | 2/14/2012 | 2/14/2012 | P | NR |
Alan Hauser
|
|
|
air balance and duct blaster contractor didn't show up
|
Conference | 2/2/2012 | 2/3/2012 | 2/3/2012 | A | CANC |
Troy Cobbley
|
|
|
kevin - 9:00 am meeting with troy - please call 1/2 hr prior Phone #: ###-####
|
Final | 1/31/2012 | 1/31/2012 | 1/31/2012 | P | PART |
Alan Hauser
|
|
|
2954 complete
|
Final | 1/30/2012 | 1/31/2012 | 1/31/2012 | A | FAIL |
Alan Hauser
|
|
|
|
Final | 1/27/2012 | 1/30/2012 | 1/31/2012 | P | NR |
Alan Hauser
|
|
|
|
Final | 1/20/2012 | 1/23/2012 | 1/23/2012 | A | FAIL |
Alan Hauser
|
|
|
duct blaster test failed
|
Rough-in | 10/14/2011 | 10/14/2011 | 10/14/2011 | P | PASS |
Troy James
|
|
|
kevin - re-inspection Phone #: ###-#### no ladder to verify balance dampers are in, mechanical contractor says their in no duct blast test done, need to witness at final
|
Rough-in | 10/7/2011 | 10/7/2011 | 10/7/2011 | P | FAIL |
Troy James
|
|
|
Phone #: ###-#### >> Inspection requested via web by Shaun Kirkman need balance dampers installed at branch takeoffs ok pressure tests to duplex
|