Final | 11/4/2011 | 11/4/2011 | 11/4/2011 | P | PASS |
Dixie Fellows
|
|
|
Scheduled final for 11/4/2011 PM. Keith Hoots can be reached at ###-#### if needed. Phone #: ###-#### >> Inspection requested via web by Katie Smith
|
Pressure Test | 11/1/2011 | 11/1/2011 | 11/1/2011 | P | PASS |
Dixie Fellows
|
|
|
reviewed manuf specs for clearance..it's ok to check the gas now...20lb gas ok...ok to set heater and call for final
|
Pressure Test | 10/31/2011 | 10/31/2011 | 10/31/2011 | P | FAIL |
Dixie Fellows
|
|
|
Scheduled pressure test for 10/31/2011 PM. Please call Toby Hoots before going out at ###-####. Phone #: ###-#### >> Inspection requested via web by Katie Smith...paper work on site didn't address the clearance issues. I have a call into the manuf and they should call me back by tomorrow
|
Pressure Test | 10/31/2011 | 10/31/2011 | 10/31/2011 | P | FAIL |
Dixie Fellows
|
|
|
Scheduled pressure test for 10/31/2011 AM if possible. Toby Hoots can be reached at ###-#### if needed. Phone #: ###-#### >> Inspection requested via web by Katie Smith...doors locked..no answer..left a message
|