Final | 3/1/2012 | 3/2/2012 | 3/1/2012 | A | PASS |
Dixie Fellows
|
|
|
oleg ###-####
|
Final | 2/28/2012 | 2/28/2012 | 2/28/2012 | P | FAIL |
Dixie Fellows
|
|
|
oleg Phone #: ###-####...remove louvers on comb air opening by w/h...shorten gas flex connector at w/h ...air balance ok
|
Final | 2/22/2012 | 2/22/2012 | 2/22/2012 | P | NR |
Dixie Fellows
|
|
|
please call builder for access -- Bill Phone #: ###-####....need air balance report
|
Rough-in | 12/1/2011 | 12/2/2011 | 12/2/2011 | P | PASS |
Dixie Fellows
|
|
|
need at 4:00 for duct blaster...R/I...20LB GAS...DUCT BLASTER OK
|
Rough-in | 12/1/2011 | 12/1/2011 | 12/1/2011 | P | PART |
Dixie Fellows
|
|
|
oleg ... r/i and p/t 20# ok waiting on duct blaster
|
Rough-in | 11/29/2011 | 11/30/2011 | 11/30/2011 | A | FAIL |
Eric Strole
|
|
|
oleg Phone #: ###-####-need approved-stamped manual j report on site for rough-in.
|
Rough-in | 11/23/2011 | 11/23/2011 | 11/23/2011 | P | FAIL |
Dixie Fellows
|
|
|
oleg Phone #: ###-####...need a manual J per troy
|