Final | 3/5/2012 | 3/5/2012 | 3/5/2012 | A | PASS |
Troy James
|
|
|
received approved air balance report
|
Final | 2/29/2012 | 3/1/2012 | 3/1/2012 | P | PEND |
Eric Strole
|
|
|
Please complete a final inspection. If there are any questions/concerns, please contact Eric @ ###-#### (HR 9/16) Phone #: ###-#### >> Inspection requested via web by Jennifer Bryan-need air balance report that is more per the manual j design.
|
Pressure Test | 1/10/2012 | 1/10/2012 | 1/10/2012 | P | PASS |
Eric Strole
|
|
|
Please complete a pressure test inspection. If there are any questions or concerns, please contact Eric @ ###-####. (HR 9/16) Phone #: ###-#### >> Inspection requested via web by Jennifer Bryan-20 lb test pass
|
Rough-in | 1/10/2012 | 1/10/2012 | 1/10/2012 | P | PASS |
Eric Strole
|
|
|
Please complete a rough-in inspection. If there are any questions or concerns, please contact Eric @ ###-####. (HR 9/16) Phone #: ###-#### >> Inspection requested via web by Jennifer Bryan-duct blast and rough-in pass.
|
Pressure Test | 1/6/2012 | 1/6/2012 | 1/6/2012 | P | CANC |
Eric Strole
|
|
|
Please complete a pressure test inspection. If there are any questions/concerns, please contact Eric @ ###-####. (HR 9/16) Phone #: ###-#### >> Inspection requested via web by Jennifer Bryan Inspection cancelled from web by: Jennifer Bryan
|
Rough-in | 1/6/2012 | 1/6/2012 | 1/6/2012 | P | CANC |
Eric Strole
|
|
|
Please complete a rough-in inspection. If there are any questions/concerns, please contact Eric @ ###-####. (HR 9/16). Phone #: ###-#### >> Inspection requested via web by Jennifer Bryan Inspection cancelled from web by: Jennifer Bryan
|