Final | 4/20/2012 | 4/20/2012 | 4/20/2012 | P | PASS |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Debbie Marino
|
Final | 4/16/2012 | 4/17/2012 | 4/17/2012 | A | PEND |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Debbie Marino-contractor will resubmit manual j. final pending.
|
Final | 4/16/2012 | 4/16/2012 | 4/16/2012 | P | FAIL |
Eric Strole
|
|
|
air balance report does not match the manual j. will meet stewart at 8:30 am to go over report.
|
Final | 4/13/2012 | 4/16/2012 | 4/16/2012 | A | NR |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Debbie Marino
|
Rough-in | 2/22/2012 | 2/22/2012 | 2/22/2012 | P | PASS |
Eric Strole
|
|
|
|
Final | 2/22/2012 | 2/22/2012 | 2/22/2012 | P | CANC |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Debbie Marino
|
Rough-in | 2/21/2012 | 2/21/2012 | 2/21/2012 | P | FAIL |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Debbie Marino-per manual j fresh air required to be 6".
|
Rough-in | 2/20/2012 | 2/21/2012 | 2/21/2012 | A | FAIL |
Eric Strole
|
|
|
Building Energy will perform the duct blast test on 2/21/12 at 10:30 am Phone #: ###-#### >> Inspection requested via web by Debbie Marino-need manual j on site for rough-in
|
Rough-in | 2/21/2012 | 2/22/2012 | 2/21/2012 | A | CANC |
Troy James
|
|
|
Phone #: ###-#### >> Inspection requested via web by Debbie Marino Inspection cancelled from web by: Debbie Marino
|
Pressure Test | 2/20/2012 | 2/21/2012 | 2/21/2012 | A | PASS |
Eric Strole
|
|
|
Building Energy will perform the duct blast test on 2/21/12 at 10:30 am Phone #: ###-#### >> Inspection requested via web by Debbie Marino-20 lb test pass
|