Final | 10/31/2012 | 11/1/2012 | 11/1/2012 | A | PASS |
Dixie Fellows
|
|
|
Contact Ben ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Flaherty...signed the card
|
Final | 10/24/2012 | 10/24/2012 | 10/24/2012 | P | PART |
Dixie Fellows
|
|
|
Contact Ben ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Flaherty...waiting for air-balance
|
Rough-in | 10/16/2012 | 10/17/2012 | 10/17/2012 | P | PART |
Dixie Fellows
|
|
|
Ben w/ TML Phone #: ###-#### >> Inspection requested via web by Michele LaMott...kitchen ceiling ok for cover
|
Rough-in | 10/4/2012 | 10/5/2012 | 10/5/2012 | A | PART |
Dixie Fellows
|
|
|
Rough in above ceiling. Contact Ben Livingston ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Flaherty...ok to cover 2nd floor lids in all areas
|
Rough-in | 9/27/2012 | 9/28/2012 | 9/28/2012 | A | PASS |
Dixie Fellows
|
|
|
Call Dave DeChambeau ###-#### Grease duct inspection Phone #: ###-#### >> Inspection requested via web by Dan Flaherty..light test and remainder of grease duct (joints) ok
|
Rough-in | 9/19/2012 | 9/20/2012 | 9/20/2012 | A | PART |
Dixie Fellows
|
|
|
Light test on grease duct. Dave Dechambeau ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Flaherty....light test on 7---8' pieces and 16 elbows and 45's ok
|
Rough-in | 9/6/2012 | 9/7/2012 | 9/7/2012 | A | PART |
Dixie Fellows
|
|
|
stan ###-####...ok to cover all hard lids
|
Rough-in | 9/5/2012 | 9/6/2012 | 9/6/2012 | P | PEND |
Dixie Fellows
|
|
|
Contact Stan Lillquist at ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Flaherty..rescheduled for fri am
|
Rough-in | 8/22/2012 | 8/23/2012 | 8/23/2012 | A | PART |
Alan Hauser
|
|
|
light test done
|