Final | 8/30/2012 | 8/30/2012 | 8/30/2012 | P | PASS |
Bill VanDegrift
|
|
|
please call john 1/2 Hr prior to arriving for access. Phone #: ###-#### >> Inspection requested via web by Nicholas Paige final ok
|
Conference | 8/29/2012 | 8/29/2012 | 8/29/2012 | P | PASS |
Dixie Fellows
|
|
|
call int gas to verify gas test was completed...called Nita with Int Gas and verified 60lb gas test ok
|
Pressure Test | 8/17/2012 | 8/21/2012 | 8/20/2012 | A | PASS |
Dixie Fellows
|
|
|
gas on roof to 3 new rtu's....###-####...60lb gas to 3 new rtu's ok
|
Final | 8/17/2012 | 8/17/2012 | 8/17/2012 | A | PART |
Dixie Fellows
|
|
|
meet at 10:00 this is a partial for new exposed spiral duct....3 new rtu's will be installed mon pm after school...they needed a temp occ. so school could open monday am
|
Conference | 8/16/2012 | 8/17/2012 | 8/17/2012 | A | PASS |
Dixie Fellows
|
|
|
partial final. please call rob with any questions Phone #: ###-#### >> Inspection requested via web by Nicholas Paige...discussed job
|
Pressure Test | 8/16/2012 | 8/17/2012 | 8/17/2012 | A | PEND |
Dixie Fellows
|
|
|
please call Doran with access questions Phone #: ###-#### >> Inspection requested via web by Nicholas Paige...the rtu's will be installed monday pm after school
|