Permit Information
Permit NumberMEC12-03609
StatusFinaled
Name HOBSON FABRICATING CORP
Site Address 7210 W BARRISTER DR
Project NamePod D Expansion of the Ada Cou
Customer NumberC7189
ePlanReviewNo
Description
Mechanical Permit - Alteration: (ADA COUNTY JAIL - POD D EXPANSION) The fire sprinkler system is required because this building is an I-3 Occupancy. To construct a 12,639 square foot prison (7,403 square foot 1st tier and 5,236 square foot 2nd tier)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final4/10/20134/11/20134/11/2013APASS
DetailsAlan Hauser
Final4/10/20134/10/20134/11/2013PPASS
DetailsAlan Hauser
Final4/3/20134/4/20134/4/2013APART
DetailsAlan Hauser
ok for tile
Rough-in2/4/20132/5/20132/5/2013APART
DetailsAlan Hauser
duct ok that comes down into cells
Rough-in12/17/201212/18/201212/18/2012APART
DetailsAlan Hauser
duct for n.e. area ok for wrap
Rough-in12/6/201212/6/201212/6/2012PPART
DetailsAlan Hauser
duct for s. area ok for cover
Rough-in11/27/201211/28/201211/28/2012APART
DetailsAlan Hauser
duct ok for wrap on rtu north/east